Journey to quench Zomba’s thirst

Listen to this article
The World Bank team visits the Zomba treatment plant
The World Bank team visits the Zomba treatment plant

In the early 1990s, concern over a special species of butterflies found on Zomba Mountain nearly denied the people of Zomba a reliable source of water. Both the Malawi Government and the World Bank, which was supporting the construction of a dam on the mountain, heeded the call not to disturb the natural habitat of the butterflies.

Almost 20 years later, the people of Zomba have a steady supply of water from a dam located at a different spot on the same mountain. Gone are the days when Zomba would grind to a halt, and Chancellor College—the largest of the University of Malawi’s colleges—would close due to dry water taps. And the butterflies still fly.

“The construction of Mulunguzi Dam high in the Zomba Plateau funded by the World Bank was the right panacea for the water problem in the district,” said Martin Chizalema, chief executive officer for Southern Region Water Board which manages water supply for Zomba.

Jaffali Kumalonje, a long-time Zomba resident, said lack of available water made life difficult. But now, things have changed.

“Building a house in Zomba was not always an attractive option when you considered the water problem,” Kumalonje said. “Now water is not a problem, even getting connected to piped water is easy.”

It has been quite a journey towards sustainable water for Malawi’s former capital city. It started in 1985 with feasibility studies for a new water supply source for the district. Construction of Mulunguzi Dam started in June 1997 and was completed in August 2001 at a cost of $28.9 million (about K1.2 billion), replete with a water treatment plant and distribution system. All this was done under the First National Water Development Project (NWDP I).

The NWDP I, whose total cost was $82.2 million (about K3.5 billion), also improved water supply services in Lilongwe and 16 other towns across the country. Further, NWDPI supported the establishment of three regional water boards—Central, Northern and Southern—complete with organisational structures, business plans and corporate charters.

According to the bank’s NWDP I implementation completion report, the Zomba water scheme eliminated the dry season water shortages in Zomba, which caused the regular closure of the university and government agencies, and suffering among local communities. Water sales also increased by 68 percent.

The Mulunguzi Dam project drives water from the uplands to the areas of distribution throughout the city. The construction of Mulunguzi Dam resulted in the creation of a reservoir with a full supply level storage volume of 3.4 million cubic metres.

Recently, a World Bank management team visited the site. The team comprised Kundhavi Kadiresan, country director of Malawi, Jonathan Kwamkwalala, sector manager for Water in Africa, and Tijan Sallah, sector manager for Agriculture, Rural Development and Irrigation.

“This dam was built to serve 25 000 people in Zomba and 100 000 from the outlying rural areas, so we should not have water shortages anymore,” said Chizalema, adding: “As a city, we are looking to the second National Water Development Plan (NWDP II), also funded by the World Bank, as a catalyst to further achieve greater access to clean water,” Kadiresan said.

The NWDP II was effective in 2007. It was designed to provide continuing support to government’s National Water Services Development Plan, which sets forth objectives, targets, actions, an investment plan and an implementation strategy for increasing water supply coverage and improving water resources management.

Through the Sector-Wide Approach (SWAP), the project contributes to Malawi’s quest to achieve the Millennium Development Goal (MDG) of reducing by half the number of people without sustainable access to improved water supply and sanitation by 2015. Malawi is on course to achieve this MDG.

In Zomba, NWPD II is helping improve operational efficiency and expand water supply. A new water treatment plant has been constructed within the site of the existing treatment plant done under NWPD I.

A total of 41.1 km of new pipelines have been laid, covering primary distribution and reinforcing the secondary distribution systems to meet future demand for a number of areas. The whole supply scheme is expected to be completed by 2016, together with similar work in other of Malawi’s fast-growing towns such as Mzuzu, Kasungu, Likuni, Mponela, Mzimba and Mangochi.

The benefits to Zomba are not only on water supply. Indirect benefits include improved health of the beneficiary population, resulting from improved quality of water and sanitation services, better hygiene practices, as well as time savings through improved access to water supply services. According to Zomba District Council Health Office, over 79.6 percent of households now have access to improved water resources. The Integrated Household Survey for Zomba indicates that the percentage of district households drawing water from unclean sources has decreased from 52 percent to 20 percent.

This spells a bright future for Zomba and its inhabitants, said Dr. Mufunanji Magalasi of Chancellor College.

“With the growing number of admission at Chancellor College due to increased demand for tertiary education, there is a boom of property development around Zomba to provide accommodation for students,” Magalasi said.

“Without the Mulunguzi Dam, which resolved our water problems, such developments would not have been possible. Maybe even some of the courses we are running may have been directed to other constituent colleges where there were minimal water problems.”

The joys of Zomba are expected to be replicated in other towns such as Mangochi, Balaka, Karonga, Salima and Nsanje where water supply schemes are also being constructed. The major cities of Blantyre, Lilongwe and Mzuzu are also benefitting under the NWDP II with rehabilitation of treatment plants and/or distribution systems. Blantyre will also benefit with designs of a new water source.

Since 2007, the World Bank has committed $175 million in NWDP II which is scheduled to close in 2016. The bank collaborates with other development partners in supporting government to achieve its goals of potable water by 2025.

Banda works in the communications department of the World Bank (Malawi).